Residential

61 Swann Rd, Taringa

The 61 Swann Rd, Taringa development is a contemporary eight-storey residential apartment building comprising 14 apartments and 33 basement car parking spaces.

Location

QLD

Client

Holtrack Properties

Architect

Ellivo

Builder

Forty4 Projects

Our Services

Hydraulic, Fire

Delivered under a Design and Construct procurement model, the project required close collaboration between the design and construction teams to coordinate revisions to the architectural and structural design while supporting efficient project delivery.

The revised design introduced changes to the apartment layout, additional residential accommodation and significant structural modifications, requiring the building services design to be reviewed and coordinated to ensure integration with the updated building form.

erbas™ | erbas™ SUSTAIN provided Hydraulic and Fire Protection engineering services, delivering the review, redesign, coordination and documentation of building services from Design Development through to Issued for Construction (IFC) documentation. Working closely with the project team, our focus was on providing practical, coordinated engineering solutions that support constructability, statutory compliance and efficient delivery.

Key Building Services

  • Review and coordination of existing hydraulic and fire protection services documentation.
  • Hydraulic and fire protection redesign to suit the revised architectural and structural design.
  • Stormwater drainage redesign to accommodate structural modifications and revised column layouts.
  • Coordination of services to minimise penetrations through transfer slab construction where practicable.
  • Early hydraulic documentation to support inground services installation and authority submissions.
  • Design Development and Issued for Construction (IFC) documentation.
  • Temporary hydraulic services to support site accommodation during construction.